Key data
| Regulation | Resolution of May 7, 2026, from the General Directorate of Energy Policy and Mines |
|---|---|
| BOE Publication | June 13, 2026 |
| Entry into force | May 7, 2026 |
| Promoter | Enel Green Power España Solar 1, SLU |
| Location | Casas de Don Pedro (Badajoz) |
| Category | Energy |
| Battery power | 38.5 MW |
| Existing solar park power | 42.295 MW |
| Resulting hybrid installation power | 50 MW |
| Processing start | October 2022 |
Enel Green Power España Solar 1, SLU can proceed with the hybridization of its Navalvillar photovoltaic park after receiving prior administrative authorization from the General Directorate of Energy Policy and Mines. The resolution, signed on May 7, 2026 and published in the BOE on June 13, 2026, closes a process initiated in October 2022 and opens the execution phase subject to technical, patrimonial and hydrological requirements.
The result is a hybrid installation of 50 MW of installed capacity that combines photovoltaic generation and battery storage at a single grid connection point.
What does this regulation establish?
The resolution grants prior administrative authorization for the storage module called "Navalvillar Battery", 38.5 MW, and for part of its evacuation infrastructure. This authorization is the first formal step in the administrative process for enabling electrical installations in Spain; it does not authorize the start of construction by itself.
The key technical and administrative elements of the resolution are:
| Element | Detail |
|---|---|
| Authorized installation | "Navalvillar Battery" storage module, 38.5 MW |
| Existing hybridized installation | "Navalvillar Solar" photovoltaic solar park, 42.295 MW |
| Result of hybridization | Hybrid installation of 50 MW installed capacity |
| Evacuation infrastructure | 30 kV underground lines to the existing Navalvillar 30/220 kV step-up substation |
| Environmental impact statement | Not required: modification of existing project without significant impact on Natura 2000 Network |
| Mandatory technical conditions | Civil protection, cultural heritage and hydrology |
| Planning permission | Mandatory before start of construction (Municipality of Casas de Don Pedro) |
| Bodies that issued favorable reports | Multiple regional and state bodies (processing initiated in October 2022) |
A relevant aspect is that the non-requirement of an environmental impact statement is justified because it is a modification of an existing project without significant impact on Natura 2000 Network areas, which simplified and accelerated the processing compared to new projects on virgin land.
Economic and operational impact
For Enel Green Power España Solar 1, SLU, the authorization represents the unblocking of a storage investment that has been in processing since October 2022. The most relevant operational effects are:
- Greater dispatch flexibility: the 38.5 MW battery allows energy generated by the solar park to be shifted to time slots with higher prices in the wholesale market.
- Optimization of the connection point: the hybrid installation operates under a single 50 MW access to the grid, taking advantage of the existing Navalvillar 30/220 kV step-up substation and avoiding the construction of new high-voltage infrastructure.
- Reduction of evacuation costs: the 30 kV underground lines connect the batteries with the existing substation, minimizing new civil works.
- Conditions that generate additional cost: compliance with civil protection, cultural heritage and hydrology conditions implies studies, corrective measures and possible design adaptations before the start of construction.
For the energy sector in general, this resolution is an example of the photovoltaic-battery hybridization model that is gaining weight in Spain: it allows maximizing the use of existing grid infrastructure and improving the profitability of already operational solar parks.
Who does it affect?
- Enel Green Power España Solar 1, SLU: direct promoter and authorization holder. Must comply with all conditions before starting construction.
- Municipality of Casas de Don Pedro (Badajoz): must process and grant municipal planning permission before the start of construction.
- Regional administration of Extremadura: involved in sectoral reports (civil protection, cultural heritage, hydrology) whose compliance is a condition of the authorization.
- Other promoters of existing solar parks: the resolution is a reference for hybridization projects with storage in already operational photovoltaic installations in Spain.
- Network operators and managers of the Navalvillar 30/220 kV substation: must coordinate the integration of the new storage module into the existing evacuation infrastructure.
Practical example
Enel Green Power has in operation the "Navalvillar Solar" solar park with 42.295 MW of photovoltaic power in Casas de Don Pedro. Without storage, all generated energy must be fed to the grid at the moment of production, which limits the ability to optimize income in the electricity market.
With the authorized hybridization, the "Navalvillar Battery" module of 38.5 MW will allow storing solar energy during peak generation hours (midday) and discharging it during periods of higher demand and price (afternoon-evening). All this without needing to build a new substation: the 30 kV underground lines will connect the batteries directly with the existing Navalvillar 30/220 kV step-up substation, reducing investment in evacuation infrastructure.
The result is a hybrid installation of 50 MW that operates under a single grid access point, with greater market value and better utilization of the existing photovoltaic asset.
What should companies do now?
- Enel Green Power España Solar 1, SLU: review and comply with the technical conditions for civil protection, cultural heritage and hydrology established in the resolution before starting any construction.
- Request municipal planning permission from the Municipality of Casas de Don Pedro: it is a mandatory prior requirement for the start of construction, it cannot be omitted even though prior administrative authorization has already been granted.
- Coordinate with regional bodies of Extremadura to verify compliance with the favorable sectoral reports issued during processing.
- Other promoters with existing solar parks studying hybridization with batteries: analyze this resolution as a procedural reference, especially regarding the non-requirement of an environmental impact statement for modifications of existing projects without impact on Natura 2000 Network.
- Verify technical coordination with the operator of the Navalvillar 30/220 kV step-up substation for the integration of the new 30 kV underground lines.
Frequently asked questions
What is prior administrative authorization and what does it allow Enel Green Power to do?
Prior administrative authorization is the first formal step in the process of enabling electrical installations in Spain. It allows the promoter to advance the project, but does not authorize the start of construction. Enel Green Power España Solar 1, SLU must comply with technical conditions (civil protection, cultural heritage and hydrology) and obtain planning permission from the Municipality of Casas de Don Pedro before beginning construction of the "Navalvillar Battery" module.
Why was an environmental impact statement not necessary for this battery?
Because it is a modification of an existing project (the Navalvillar solar park, already in operation) and the evaluation determined that there is no significant impact on Natura 2000 Network areas. This circumstance simplified the processing compared to new projects on land without prior intervention.
How long did the processing of this authorization take?
Processing began in October 2022 and the resolution was signed on May 7, 2026, which represents approximately three and a half years of administrative process, with favorable reports from multiple regional and state bodies.
How will the battery be connected to the electrical grid?
Through 30 kV underground lines that will connect the "Navalvillar Battery" storage module with the existing Navalvillar 30/220 kV step-up substation. This avoids the construction of new high-voltage infrastructure and reduces the necessary investment.
What total power will the resulting hybrid installation have?
The resulting hybrid installation will have an installed capacity of 50 MW, combining the 42.295 MW of the "Navalvillar Solar" photovoltaic solar park with the 38.5 MW of the new "Navalvillar Battery" battery storage module, all in Casas de Don Pedro (Badajoz).
Official source
Consult complete regulation in official source
Notice: This article is for informational purposes only and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-12861