Summary

The environmental impact report is approved for a 35 MW energy storage system linked to a solar plant in Palencia. It allows progress in the hybridization of renewable energies with storage.

Detailed analysis PRO

The Dirección General de Calidad y Evaluación Ambiental issues the environmental impact report for the 35 MW BESS module intended to be hybridized with the Virgen de Areños III photovoltaic plant (44.681 MW) in Palencia. This report is an essential administrative procedure that enables the continuation of the energy pr…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Crear cuenta gratis Ver planes PRO

Full official title

Resolución de 10 de marzo de 2026, de la Dirección General de Calidad y Evaluación Ambiental, por la que se formula informe de impacto ambiental del proyecto «Módulo de almacenamiento BESS hibridación FV Virgen de Areños III, de 35 MW de potencia instalada, para su hibridación con la planta solar FV Virgen de Areños III, de 44,681 MW, y para parte de su evacuación, en la provincia de Palencia».

Related regulations