Energy BOE Importance: 3/10

Authorization to build the La Plana-Morella high-voltage power line in Castellón

22 Jun 2026 Effective: 22 Jun 2026 5 views
Who is affected:
Red Eléctrica de España, landowners in 16 municipalities of Castellón affected by the power line

Summary

The Government authorizes Red Eléctrica to build a 400 kV aerial line of 86 km in the province of Castellón. The infrastructure will connect the La Plana and Morella substations crossing 16 municipalities.

Detailed analysis PRO

The Directorate General for Energy Policy and Mines grants Red Eléctrica de España, SAU, administrative authorization for construction of the double-circuit aerial line at 400 kV 'La Plana-Morella 2 and 3', with an approximate length of 86 km in the province of Castellón. The proceedings, initiated in 2009, also includ…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Crear cuenta gratis Ver planes PRO

Full official title

Resolución de 8 de junio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Red Eléctrica de España, SAU, autorización administrativa de construcción para la línea aérea de transporte de energía eléctrica, doble circuito a 400 kV, «La Plana-Morella 2 y 3», en Almassora, Castelló de la Plana, Borriol, Sant Joan de Moró, Vilafamés, Vall d'Alba, Les Useres, Culla, Atzeneta del Maestrat, La Torre d'En Besora, Benassal, Vilafranca, Ares del Maestrat, Castellfort, Cinctorres y Morella (Castellón), así como autorización administrativa previa y autorización administrativa de construcción para las modificaciones introducidas en la «Adenda 3», y se declara, en concreto, la utilidad pública.

Sponsored space
Sponsor the Energy category

Your brand in front of thousands of businesses and freelancers tracking the legal changes in your sector.

I want to sponsor it

Related regulations