Energías Alternativas Eólicas Riojanas withdraws from its wind and solar repowering project in Pradejón and Calahorra. The regulatory change on power calculation transfers competence to the Government of La Rioja.
Detailed analysis
PRO
Energías Alternativas Eólicas Riojanas, SL requested authorization in September 2025 to repower the Raposeras wind farm (40.5 MW) and hybridize it with photovoltaic installation (16.89 MW) and storage (5 MW) in La Rioja. Following the approval of Real Decreto 997/2025, which redefined the calculation of installed capac…
Full official title
Resolución de 8 de mayo de 2026, de la Dirección General de Política Energética y Minas, por la que se acepta el desistimiento formulado por Energías Alternativas Eólicas Riojanas, SL, de la solicitud de autorización administrativa previa para el proyecto de repotenciación del parque eólico «Raposeras», de 40,5 MW de potencia instalada, y su hibridación con el parque solar fotovoltaico «Raposeras», de 16,89 MW de potencia instalada, y el sistema de almacenamiento «Raposeras», de 5 MW de potencia instalada, en Pradejón y Calahorra (La Rioja), y para su infraestructura de evacuación.