Authorization denied for a 110 MW wind farm in Burgos

04 Apr 2026 Effective: 19 Mar 2026 24 views
Who is affected:
Company Aloreña Wind, SL and the renewable energy sector in Burgos

Summary

The Dirección General de Política Energética denies the permit to build the Satarrubla wind farm in Burgos. The company Aloreña Wind will not be able to develop this 110 MW wind energy installation.

Detailed analysis PRO

The Dirección General de Política Energética y Minas has rejected the prior administrative authorization request submitted by Aloreña Wind, SL for the 110 MW Satarrubla wind farm in the province of Burgos, including its evacuation infrastructure. This resolution represents a significant setback for the project, which w…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Crear cuenta gratis Ver planes PRO

Full official title

Resolución de 19 de marzo de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Aloreña Wind, SL, de autorización administrativa previa de la instalación eólica Satarrubla, de 110 MW de potencia instalada, y de su infraestructura de evacuación, en la provincia de Burgos.