Energy BOE Importance: 3/10

Authorization Denied for Yadisema Phase II 63.83 MW Solar Plant in Toledo

11 Jun 2026 Effective: 11 Jun 2026 43 views
Who is affected:
Promoters of photovoltaic and renewable installations processing authorizations in Spain

Summary

The Ministry denies Energías Renovables Yadisema SL authorization to build a 63.83 MW solar plant in Toledo due to expiration of grid access and connection permits.

Detailed analysis PRO

The General Directorate of Energy Policy and Mines rejects the authorization request for the Yadisema Phase II photovoltaic plant (63.83 MW) in Toledo. The main reason is the expiration, on October 1, 2024, of the access and connection permits to the transmission network at the Leganés 220 kV substation of Red Eléctric…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Crear cuenta gratis Ver planes PRO

Full official title

Resolución de 4 de marzo de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Energías Renovables Yadisema, SL, de autorización administrativa previa de modificaciones y autorización administrativa de construcción de la instalación fotovoltaica Yadisema Fase II, de 63,83 MW de potencia instalada, y de su infraestructura de evacuación, en la provincia de Toledo.