Enel Green Power withdraws its application to build the 110 MW Trabadelo wind farm in León
08 Apr 2026
Effective: 19 Mar 2026
11 views
Who is affected:
Enel Green Power España and municipalities in the Bierzo region (León) involved in the wind farm project
Summary
Enel Green Power España withdraws from its 110 MW wind farm project in several municipalities in León. The administration formally accepts the withdrawal of the application.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines accepts the withdrawal by Enel Green Power España, SL, regarding the prior administrative authorization for the Trabadelo wind farm, with 110 MW of installed capacity. The project affected eleven municipalities in the Bierzo region of León, including Ponferrada and Vi…
Full official title
Resolución de 19 de marzo de 2026, de la Dirección General de Política Energética y Minas, por la que se acepta el desistimiento formulado por Enel Green Power España, SL, de la solicitud de autorización administrativa previa para el parque eólico Trabadelo, de 110 MW de potencia instalada, y su infraestructura de evacuación, en Trabadelo, Barjas, Corullón, Toral de los Vados, Cacabelos, Villafranca del Bierzo, Arganza, Sancedo, Camponaraya, Cabañas Raras y Ponferrada (León).